Welcome!

Apache Authors: Dmitriy Stepanov, Yeshim Deniz, Pat Romanski, Lacey Thoms, Sandi Mappic

News Feed Item

Commonwealth Silver and Gold Completes Positive Preliminary Economic Assessment for the Commonwealth Project, Cochise County, Arizona

TORONTO, ONTARIO -- (Marketwired) -- 02/13/14 -- Commonwealth Silver and Gold Mining Inc. ("Commonwealth Silver and Gold" or the "Company") is pleased to provide the results that will be reported in its Preliminary Economic Assessment ("PEA") for the 98% controlled Commonwealth gold and silver project in Cochise County, Arizona, approximately 120 km (75 miles) southeast of Tucson. The PEA was completed in accordance with National Instrument 43-101 ("NI 43-101") by Hard Rock Consulting, LLC ("HRC") of Lakewood, Colorado. All dollar amounts are in United States dollars unless otherwise stated.

All NPV amounts, IRR and payback period are based on the Company's 98% share of Project economics. All mining statistics, production, capital and closure amounts are to 100%. Highlights from the base case study at $1,350 per ounce gold, $22.50 per ounce silver and based solely on estimated Measured and Indicated mineral resources include:


--  Pre-tax Net Present Value ("NPV") at a 5% discount rate of $141.0
    million and a pre-tax Internal Rate of Return ("IRR") of 74.9%; 
--  After-tax NPV at a 5% discount rate of $101.3 million and IRR of 58.2%; 
--  After-tax payback of 1.6 years; 
--  Pre-production capital cost ("CAPEX") of $27.2 million including a 20%
    contingency; 
--  Remaining advance royalty payment $4.1 million and start-up working
    capital of $13.5 million until positive cash flow from leaching is
    achieved; 
--  Sustaining capital of $20.6 million (100%) over life of mine ("LOM")
    including a 20% contingency and reclamation, net of salvage values of
    $8.4 million; 
--  An 8.7 year mine life, mining and processing 31.2 million tonnes of ore
    at 10,000 tpd, averaging 0.39 grams per tonne ("g/t") gold and 32.0 g/t
    silver; 
--  An overall strip ratio of 0.97:1; 
--  Average annual payable metal production of 35,800 ounces of gold and 1.3
    million ounces of silver for total LOM production of approximately
    312,000 ounces of gold and 10.9 million ounces of silver;  
--  Average annual gold equivalent ("AuEq") production of 57,000 ounces AuEq
    at 60:1 gold to silver ratio, peaking at approximately 69,000 ounces
    AuEq in year 7; 
--  Gold Institute Cost Standard, LOM total cash operating costs are
    estimated to be approximately $831 per gold equivalent ounce; 
--  The HRC PEA has been constrained to the mineral resource estimate
    contained within a pit located entirely on the Company's patented mining
    claims and does not take into account the potential for additional
    mineralization on the adjoining unpatented mining claims or the
    potential for mineralization at the nearby Blue Jeep and San Ignacio
    exploration targets, all of which have the potential to extend the
    current projected life of the overall project or augment the economics
    of future years. Currently, there are no additional estimated mineral
    resources on any of these areas that are in compliance with NI 43-101. 

Michael Farrant, President and CEO stated, "We are extremely pleased with this Preliminary Economic Assessment. It demonstrates that the Commonwealth Project is one of the best undeveloped precious metals projects in the world based on after-tax IRR and after-tax NPV relative to the capital required to put the Project into production. The Project sits on private land in a mining friendly jurisdiction surrounded by first rate infrastructure. Most importantly, given the size of the Project relative to the market capitalization of the Company, this is a Project that can get built and those are exactly the kinds of projects that are retaining a superior valuation in the changing global mining landscape. The Commonwealth Project is currently projected to become the largest operating gold mine in the state of Arizona. As a Company, we have continued to deliver against our originally stated plans and I am very pleased with the work performed by everyone that contributed to the completion of this PEA."

The sensitivity table below shows the pre-tax and after-tax NPV, IRR and payback period at different gold prices, with the corresponding silver price calculated at a 60:1 gold to silver ratio.


----------------------------------------------------------------------------
                                                                      After-
                                           Pre-             Pre-tax      tax
Au Price    Ag Price   Pre-tax After-tax    tax    After-   Payback  Payback
Per Ounce  Per Ounce  NPV ($M)  NPV ($M)    IRR   tax IRR   (Years)  (Years)
----------------------------------------------------------------------------
$1,050      $  17.50  $   34.2  $   22.3   24.7%     18.6%      2.6      5.2
----------------------------------------------------------------------------
$1,125      $  18.75  $   60.9  $   42.7   38.2%     29.6%      2.2      2.5
----------------------------------------------------------------------------
$1,200      $  20.00  $   87.7  $   62.4   50.9%     39.6%      1.8      2.1
----------------------------------------------------------------------------
$1,275      $  21.25  $  114.3  $   81.8   63.1%     49.1%      1.5      1.8
----------------------------------------------------------------------------
$1,350      $  22.50  $  141.0  $  101.3   74.9%     58.2%      1.3      1.6
----------------------------------------------------------------------------
$1,425      $  23.75  $  167.7  $  120.4   86.5%     67.0%      1.0      1.4
----------------------------------------------------------------------------
$1,500      $  25.00  $  194.4  $  138.7   97.9%     75.1%      1.0      1.3
----------------------------------------------------------------------------
$1,575      $  26.25  $  221.1  $  156.4  109.1%     82.4%      0.8      1.1
----------------------------------------------------------------------------
$1,650      $  27.50  $  247.7  $  174.1  120.3%     89.7%      0.7      1.0
----------------------------------------------------------------------------
                                                                         
                                                                         
Table 1: Mine Plan Highlights                                            
                                                                         
-------------------------------------------------------------------------
Summary of Results                                  Unit            Value
-------------------------------------------------------------------------
Mine Life                                          Years              8.7
-------------------------------------------------------------------------
Total ore to leach pads                         M tonnes             31.2
-------------------------------------------------------------------------
Total waste                                     M tonnes             30.3
-------------------------------------------------------------------------
Strip ratio                                          w:o           0.97:1
-------------------------------------------------------------------------
Total re-handled                                M tonnes              5.3
-------------------------------------------------------------------------
Total moved                                     M tonnes             66.8
-------------------------------------------------------------------------
Ore mining rate                                      tpd           10,000
-------------------------------------------------------------------------
Average grade to pad - Au                            g/t             0.39
-------------------------------------------------------------------------
Average grade to pad - Ag                            g/t             32.0
-------------------------------------------------------------------------
Cumulative recovery - Au                              %             79.5%
-------------------------------------------------------------------------
Cumulative recovery - Ag                              %             34.2%
-------------------------------------------------------------------------
LOM production - Au                               ounces          311,534
-------------------------------------------------------------------------
LOM production - Ag                               ounces       10,926,367
-------------------------------------------------------------------------
LOM production - AuEq (60:1)                      ounces          493,640
-------------------------------------------------------------------------
Average annual production - Au                    ounces           35,809
-------------------------------------------------------------------------
Average annual production - Ag                    ounces        1,255,904
-------------------------------------------------------------------------
Average annual production - AuEq (60:1)           ounces           56,740
-------------------------------------------------------------------------
-------------------------------------------------------------------------
                                                                            
                                                                            
Table 2: Economic Highlights                                                
                                                                            
----------------------------------------------------------------------------
Summary of Results                                Value ($ M)      $/oz AuEq
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
 LOM revenue - ($1,350/oz. Au, $22.50/oz. Ag)          $666.4         $1,350
----------------------------------------------------------------------------
 LOM operating costs:                                                       
----------------------------------------------------------------------------
  Mining (including 2.5% contingency)                   182.2            369
----------------------------------------------------------------------------
  Processing (including 2.5% contingency)               190.9            387
----------------------------------------------------------------------------
  Site G&A (including 2.5% contingency)                  19.9             40
----------------------------------------------------------------------------
  Property and other taxes                                5.3             10
----------------------------------------------------------------------------
  Royalties                                               8.2             17
----------------------------------------------------------------------------
  Transportation and refining                             3.8              8
----------------------------------------------------------------------------
Total LOM cash operating costs                          410.3            831
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Capital and closure costs:                                                  
----------------------------------------------------------------------------
  Pre-production capital                                 23.0             46
----------------------------------------------------------------------------
  Pre-production contingency (20%)                        4.2              9
----------------------------------------------------------------------------
Total pre-production capital                             27.2             55
----------------------------------------------------------------------------
  Sustaining capital                                     17.2             35
----------------------------------------------------------------------------
  Sustaining capital contingency (20%)                    3.4              7
----------------------------------------------------------------------------
Total sustaining capital                                 20.6             42
----------------------------------------------------------------------------
Closure costs net of salvage values                       8.4             17
----------------------------------------------------------------------------
Total capital and closure costs (including                                  
 contingency)                                            56.2            114
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Other cash outflows:                                                        
----------------------------------------------------------------------------
  Income taxes                                           53.5            108
----------------------------------------------------------------------------
  Other                                                   4.1              8
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Total after-tax cash flow                              $142.3           $289
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Unit costs                                               Unit          Value
----------------------------------------------------------------------------
  Cost per tonne mined - 61,426,774 tonnes            $/tonne          $2.97
----------------------------------------------------------------------------
  Cost per tonne processed - 31,153,575                                     
   tonnes                                             $/tonne          $6.13
----------------------------------------------------------------------------
  Cost per tonne site G&A - 31,153,575 tonnes         $/tonne          $0.64
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Mineral Resource Statement for the Commonwealth Gold and Silver Project:

The Mineral Resource estimate, before designing an engineered pit, is based on a 3D geologic model constructed using geologic and assay data from approximately 23,085 meters of drilling in 208 drill holes (155 historic and 43 drilled by the Company) and 2,984 meters of channel sampling in 209 channel sample lines. The assay data was examined for the presence of high grade outlier data which could potentially adversely impact the grade estimation. Based on this analysis, all gold and silver assays were capped at 10.0 g/t and 1,000.0 g/t, respectively. The capped assay data were then composited into 4.0m down-hole lengths for use in grade estimation. Block grades were estimated using inverse distance weighting ("IDW") interpolation methods, specifically ID2.5. The Mineral Resource estimate stated above a 0.2 g/t gold equivalent ("AuEq") cut-off grade is stated below in Table 3.


                                                                            
Table 3: Mineral Resource Statement for the Commonwealth Gold-Silver        
Deposit, Cochise County, Arizona, Hard Rock Consulting, LLC, November 30,   
2013(i)                                                                     
----------------------------------------------------------------------------
                                                    Contained Metal (Ounces)
                                          ----------------------------------
                       Au       Ag    AuEq                                  
Cut-off     Tonnes   Grade   Grade   Grade                                  
(g/t)       ('000)   (g/t)   (g/t)   (g/t)        Au           Ag       AuEq
----------------------------------------------------------------------------
            Inverse Distance 2.5 Model In Pit Measured Resources            
----------------------------------------------------------------------------
0.4          4,069    0.57    48.6    1.38    74,800    6,357,700    180,800
----------------------------------------------------------------------------
0.3          4,504    0.53    45.0    1.28    77,200    6,516,900    185,700
----------------------------------------------------------------------------
0.2          5,007    0.49    41.3    1.18    79,000    6,648,500    189,800
----------------------------------------------------------------------------
            Inverse Distance 2.5 Model In Pit Indicated Resources           
----------------------------------------------------------------------------
0.4         21,934    0.45    36.8    1.06   314,500   25,950,900    746,100
----------------------------------------------------------------------------
0.3         26,643    0.40    32.2    0.93   339,200   27,582,000    799,200
----------------------------------------------------------------------------
0.2         30,623    0.36    29,1    0.85   354,400   28,650,600    832,000
----------------------------------------------------------------------------
                   In Pit Measured and Indicated Resources                  
----------------------------------------------------------------------------
0.4         26,003    0.47    38.6    1.11   389,300   32,308,600    926,900
----------------------------------------------------------------------------
0.3         31,147    0.42    34.1    0.98   416,400   34,098,900    984,900
----------------------------------------------------------------------------
0.2         35,630    0.38    30.8    0.89   433,400   35,299,100  1,021,800
----------------------------------------------------------------------------
                Inverse Distance 2.5 Model Inferred Resources               
----------------------------------------------------------------------------
0.4          7,380    0.29    17.2    0.58    67,900    4,075,100    136,700
----------------------------------------------------------------------------
0.3         12,974    0.25    13.8    0.48   102,800    5,762,000    199,600
----------------------------------------------------------------------------
0.2         18,733    0.21    11.6    0.41   127,600    6,998,200    245,400
----------------------------------------------------------------------------


(i)Notes:                                                                   
(1) Mineral Resources are not Mineral Reserves and do not have demonstrated 
economic viability. There is no certainty that all or any part of the       
Mineral Resources estimated will be converted into Mineral Reserves.        
(2) Measured and Indicated Mineral Resources captured within the pit shell  
meet the test of reasonable prospect for economic extraction and can be     
declared a Mineral Resource.                                                
(3) Inferred Mineral Resources are that part of the Mineral Resource for    
which the quantity and grade or quality are estimated on the basis of       
geological evidence and limited sampling and reasonably assumed, but not    
verified, geological and grade continuity.                                  
(4) All resources are stated above a 0.2 g/t gold equivalent ("AuEq") cut-  
off.                                                                        
(5) Pit optimization is based on assumed gold and silver prices of          
US$1,350/oz. and US$22.50/oz., respectively and mining, processing and G&A  
costs of US$7.25 per tonne. Metallurgical recoveries for gold and silver    
were assigned by lithologic unit.                                           
(6) Mineral resource tonnage and contained metal have been rounded to       
reflect the accuracy of the estimate, and numbers may not add due to        
rounding.                                                                   
(7) Gold Equivalent stated using a ratio of 60:1 and ounces calculated using
the following conversion rate: 1 troy ounce = 31.1035 grams. Metallurgical  
recoveries are not accounted for in the gold equivalent calculation.        

Mineral Resource Estimates Used for Economic Assessment in the PEA:

The estimated Mineral Resource contained within the PEA includes 28.3 million tonnes at a 0.3 g/t AuEq cut-off and an additional 2.8 million tonnes of lower grade ore at a 0.24 g/t AuEq cut-off and is presented in Table 4. This represents the estimated Mineral Resource contained within the preliminary engineered pit design which includes haul roads. The PEA is preliminary in nature and it is important to note that the Mineral Resources described herein are not mineral reserves and, as such, do not have demonstrated economic viability. There is no certainty that the preliminary economic assessment will be realized.


                                                                            
Table 4: Measured and Indicated Resources within Pit Design                 
----------------------------------------------------------------------------
                                                    Contained Metal (Ounces)
                                               -----------------------------
                                Au     Ag  AuEq                             
Pit      Resource     Tonnes Grade  Grade Grade                             
 Phase    Category    ('000) (g/t)  (g/t) (g/t)      Au          Ag     AuEq
----------------------------------------------------------------------------
Phase 1  Measured      3,253  0.46  43.07  1.18  48,034   4,504,874  123,115
----------------------------------------------------------------------------
Phase 1  Indicated    12,227  0.36  34.57  0.94 142,539  13,590,165  369,042
----------------------------------------------------------------------------
         Measured +                                                         
Phase 1   Indicated   15,480  0.38  36.36  0.99 190,573  18,095,039  492,157
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Phase 2  Measured      1,633  0.56  38.17  1.19  29.212   2,003,915   62,610
----------------------------------------------------------------------------
Phase 2  Indicated    14.040  0.38  26.37  0.82 172,644  11,902,972  371,027
----------------------------------------------------------------------------
         Measured +                                                         
Phase 2   Indicated   15,673  0.40  27.60  0.86 201,856  13,906,886  433,637
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total                                                                       
 All                                                                        
 Phases  Measured      4,886  0.49  41.43  1.18  77,245   6,508,788  185,725
----------------------------------------------------------------------------
Total                                                                       
 All                                                                        
 Phases  Indicated    26,267  0.37  30.19  0.88 315,184  25,493,137  740,069
----------------------------------------------------------------------------
Total                                                                       
 All     Measured +                                                         
 Phases   Indicated   31,154  0.39  31.95  0.92 392,429  32,001,925  925,794
----------------------------------------------------------------------------
----------------------------------------------------------------------------
1) Mineral Resources are not Mineral Reserves and do not have demonstrated  
economic viability. There is no certainty that all or any part of the       
Mineral Resources estimated will be converted into Mineral Reserves.        
2) Prepared by Jeff Choquette, P.E., Mining Engineer, an independent        
Qualified Person within the meaning of NI 43-101, using a reporting cut-off 
grade of 0.24 g/t AuEq.                                                     
3) Gold Equivalent stated using a ratio of 60:1 and ounces calculated using 
the following conversion rate: 1 troy ounce = 31.1035 grams.  Metallurgical 
recoveries are not accounted for in the gold equivalent calculation.        

(i)Total Measured and Indicated ("M&I") resources are inclusive of the M&I resources limited to the optimized ultimate pit boundary and as such Table 4 summarizes resources contained within the pit design only.

Mining and Crushing

The mine plan developed for the PEA mines the Commonwealth deposit in two phases. The phase one pit containing 15.48 million ore tonnes is mined during years 1 to 4. During years 1 to 3, the average strip ratio is 0.66:1. During year 4, mining begins to transition into the phase two pit containing 15.67 million ore tonnes. The average strip ratio over years 4 to 6 is 1.66:1 while during years 7 to 9 the average strip ratio falls to 0.42:1.

Standard open pit mining methods are utilized involving typical drilling, blasting and material movement. The 31.2 million ore tonnes to be placed on the leach pads are comprised of five different rock types. Three of these rock types comprising 19.43 million ore tonnes (62%) are required to be crushed to 1/2 inch. Two of these rock types comprising 11.72 million ore tonnes (38%) are required to be crushed to 1/8 inch and agglomerated.


                                                                            
Table 5: Crush Size, Recovery and Ore Tonnage by Rock Type                  
-------------------------------------------------------------
                                  Recoveries (%)             
-------------------------------------------------------------
Rock Type          Crush Size       Au        Ag   Tonnes (M)
-------------------------------------------------------------
Rhyolite                 1/8"     78.0      30.0         7.34
-------------------------------------------------------------
Vein                     1/8"     79.0      49.0         4.38
-------------------------------------------------------------
Lower Andesite           1/2"     81.0      33.0         4.63
-------------------------------------------------------------
Upper Andesite           1/2"     78.0      35.0         6.11
-------------------------------------------------------------
Bisbee                   1/2"     80.0      23.0         8.69
-------------------------------------------------------------
Total                             79.5      34.2        31.15
-------------------------------------------------------------

The Company received a quote from a contractor to perform all of the drilling, blasting, material movement and crushing to mine plan specifications. This quote has been included in the PEA.

Processing

The Commonwealth Project will use a (flow rate) Merrill-Crowe gold and silver recovery plant using zinc precipitation to recover gold and silver from cyanide solution. The process plant will operate 24 hours per day and 365 days per year at a rate of 3,000 gallons per minute. The process plant will produce dore with approximately 97% of the precious metal content being silver and 3% being gold.

Infrastructure

The Commonwealth Project is accessible by paved highway. Currently a 14.4 KvA powerline services the property with 60 amp service. The PEA envisions upgrading the trunk powerline from the Apache Generating Station located 19km (11 miles) from the Project site at a cost of approximately $358,000. Water is planned to be sourced from regional groundwater sources.

Capital Costs

The initial capital requirement for the Project to 100% is estimated to be $27.2 million, sustaining capital of $20.6 million and net closure costs of $8.4 million as detailed in the table below. A contingency of $7.6 million is included in the $56.2 million total.


                                                                            
Table 6: Commonwealth Project Capital and Closure Costs                     
--------------------------------------------------------------
Capital and Closure Costs                         $ (millions)
--------------------------------------------------------------
Pre-production Capital Costs                                  
--------------------------------------------------------------
Conveying equipment                                        4.8
--------------------------------------------------------------
Merrill-Crowe plant and equipment                          2.5
--------------------------------------------------------------
Truck shop, assay lab and buildings                        4.5
--------------------------------------------------------------
Haul roads and access road                                 1.2
--------------------------------------------------------------
Leach pad and ponds                                        4.9
--------------------------------------------------------------
Off-site infrastructure                                    0.7
--------------------------------------------------------------
Owner's cost and indirects                                 3.1
--------------------------------------------------------------
Surface rights                                             1.3
--------------------------------------------------------------
Total pre-production initial capital costs                23.0
--------------------------------------------------------------
Contingency                                                4.2
--------------------------------------------------------------
Total pre-production capital costs                        27.2
--------------------------------------------------------------
Sustaining Capital Costs                                      
--------------------------------------------------------------
Leach pads                                                 8.9
--------------------------------------------------------------
Merrill-Crowe plant and equipment                          8.3
--------------------------------------------------------------
Contingency                                                3.4
--------------------------------------------------------------
Total sustaining capital                                  20.6
--------------------------------------------------------------
Reclamation and closure costs                             12.3
--------------------------------------------------------------
Salvage values - mine and other                          (2.6)
--------------------------------------------------------------
Salvage values - land                                    (1.3)
--------------------------------------------------------------
Closure costs net of salvage values                        8.4
--------------------------------------------------------------
Total capital and closure costs                           56.2
--------------------------------------------------------------

Financial Analysis and Sensitivities

Using a gold price of $1,350 per ounce and a silver price of $22.50 per ounce, the PEA yields a pre-tax NPV at 5% of $141.0 million and IRR of 74.9% with a payback period of 1.3 years. After-tax NPV at 5% amounts to $101.3 million, and IRR of 58.2% and a payback period of 1.6 years.


Table 7: Project NPV Sensitivity to Discount Rates                          
------------------------------------------------
Discount Rate      Pre-tax NPV     After-tax NPV
------------------------------------------------
0%                      $195.8            $142.3
------------------------------------------------
5%                      $141.0            $101.3
------------------------------------------------
8%                      $115.6             $82.0
------------------------------------------------
10%                     $101.3             $71.2
------------------------------------------------

Qualified Persons and Contributors

The Technical Report and Preliminary Economic Assessment for the Commonwealth Silver and Gold Project was prepared by Hard Rock Consulting, LLC of Lakewood, Colorado, with the following Qualified Persons, as defined by NI 43-101, each of whom is independent of the Company, contributing to their respective sections:

Qualified Persons

Zachary Black - QP-SME-RM, Geology, Resource Modeling

J. J. Brown - P.G., QP-SME-RM, Geology, Overall Report Content

Jeff Choquette - P.E., QP-MMSA, Mine Planning, Economic Modelling, Mine Management

Deepak Malhotra, Resource Development Inc - Ph.D., QP-MMSA, Metallurgy

Additional Contributors:

Don Beesley - B.Sc., Project Management, Scheduling, Estimating

Mark Shonnard - B.A. (Hons), CPA, Economic Modeling, Financial Analysis

Kenn Zerby - B.Sc., Mechanical Engineering, Graphics and Drafting

Each of the consultants has reviewed and approved this news release. In addition, the foregoing technical information has also been reviewed by Mr. Hall Stewart, Vice President, Exploration for Commonwealth Silver and Gold and a Qualified Person for the purpose of NI 43-101.

Technical Report

A copy of the full NI 43-101 Technical Report will be available on the Company's website at www.commonwealthsilver.ca within 45 days.

About Commonwealth Silver and Gold Mining Inc.

Commonwealth Silver and Gold is a private Canadian mineral exploration and development company focused on acquiring gold and silver properties in politically stable, mining friendly jurisdictions and advancing its flagship Commonwealth Project in Arizona towards production. The Company comprises an experienced management group with a strong background in acquisition, exploration, development and financing of precious metals mining projects.

For further information on Commonwealth Silver and Gold please visit www.commonwealthsilver.ca.

CAUTIONARY NOTE TO U.S. INVESTORS CONCERNING ESTIMATES OF MEASURED, INDICATED AND INFERRED MINERAL RESOURCES:

Information concerning the properties of Commonwealth Silver and Gold has been prepared in accordance with Canadian standards under applicable Canadian securities laws and may not be comparable to similar information for United States companies. This news release uses the terms "Mineral Resource", "Measured Mineral Resource", "Indicated Mineral Resource" and "Inferred Mineral Resource" which are Canadian mining terms as defined in and required to be disclosed by NI 43-101 under guidelines set out in the CIM standard "CIM Definition Standards - For Mineral Resources and Reserves". While the terms "Mineral Resource", "Measured Mineral Resource", "Indicated Mineral Resource" and "Inferred Mineral Resource" are recognized and required by Canadian regulations, they are not defined terms under standards of the United States Securities and Exchange Commission (the "SEC"). The estimation of measured and indicated Mineral Resources involves greater uncertainty as to their existence and economic feasibility than the estimation of proven and probable reserves. U.S. investors are cautioned not to assume that measured and indicated Mineral Resources will be converted into reserves. The estimation of inferred Mineral Resources involves far greater uncertainty as to their existence and economic viability than the other categories of estimated Mineral Resources. It cannot be assumed that all or any part of an "Inferred Mineral Resource" will ever be upgraded to a higher category. Under Canadian rules, estimates of Inferred Mineral Resources may not form the basis of feasibility or other economic studies. Readers are also cautioned not to assume that all or any part of Measured or Indicated Resources will ever be converted to Mineral Reserves. Additionally, readers are cautioned not to assume that all or any part of an "Inferred Mineral Resource" exists, or is economically mineable.

Disclosure of "contained ounces" in an estimated Mineral Resource is permitted disclosure under Canadian regulations, however the SEC normally only permits issuers to report mineralization that does not constitute "reserves" by SEC standards as in place tonnage and grade without reference to unit measures. Accordingly, the information contained in this news release may not be comparable to similar information made public by U.S. companies that are not subject to NI 43-101.

CAUTIONARY NOTE REGARDING FORWARD LOOKING INFORMATION

This news release contains certain "forward-looking information" under Canadian securities laws. All statements that address future plans, activities, events or developments that the Company believes, expects or anticipates will or may occur are forward-looking information. This can include, but is not limited to comments regarding the timing and content of upcoming work programs, geological interpretations, receipt of property titles, potential mineral recovery processes etc. Forward-looking information addresses future events and conditions and therefore involves inherent risks and uncertainties. There can be no assurance that outcomes anticipated in the forward-looking information will occur and actual results may differ materially from those currently anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking information. The Company undertakes no obligation to update publicly or otherwise any forward-looking information, except as may be required by law.

No stock exchange, regulation securities provider, securities commission or other regulatory authority has approved or disapproved the information contained in this news release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
Software AG helps organizations transform into Digital Enterprises, so they can differentiate from competitors and better engage customers, partners and employees. Using the Software AG Suite, companies can close the gap between business and IT to create digital systems of differentiation that drive front-line agility. We offer four on-ramps to the Digital Enterprise: alignment through collaborative process analysis; transformation through portfolio management; agility through process automation and integration; and visibility through intelligent business operations and big data.
There will be 50 billion Internet connected devices by 2020. Today, every manufacturer has a propriety protocol and an app. How do we securely integrate these "things" into our lives and businesses in a way that we can easily control and manage? Even better, how do we integrate these "things" so that they control and manage each other so our lives become more convenient or our businesses become more profitable and/or safe? We have heard that the best interface is no interface. In his session at Internet of @ThingsExpo, Chris Matthieu, Co-Founder & CTO at Octoblu, Inc., will discuss how these devices generate enough data to learn our behaviors and simplify/improve our lives. What if we could connect everything to everything? I'm not only talking about connecting things to things but also systems, cloud services, and people. Add in a little machine learning and artificial intelligence and now we have something interesting...
Last week, while in San Francisco, I used the Uber app and service four times. All four experiences were great, although one of the drivers stopped for 30 seconds and then left as I was walking up to the car. He must have realized I was a blogger. None the less, the next car was just a minute away and I suffered no pain. In this article, my colleague, Ved Sen, Global Head, Advisory Services Social, Mobile and Sensors at Cognizant shares his experiences and insights.
We are reaching the end of the beginning with WebRTC and real systems using this technology have begun to appear. One challenge that faces every WebRTC deployment (in some form or another) is identity management. For example, if you have an existing service – possibly built on a variety of different PaaS/SaaS offerings – and you want to add real-time communications you are faced with a challenge relating to user management, authentication, authorization, and validation. Service providers will want to use their existing identities, but these will have credentials already that are (hopefully) irreversibly encoded. In his session at Internet of @ThingsExpo, Peter Dunkley, Technical Director at Acision, will look at how this identity problem can be solved and discuss ways to use existing web identities for real-time communication.
Can call centers hang up the phones for good? Intuitive Solutions did. WebRTC enabled this contact center provider to eliminate antiquated telephony and desktop phone infrastructure with a pure web-based solution, allowing them to expand beyond brick-and-mortar confines to a home-based agent model. It also ensured scalability and better service for customers, including MUY! Companies, one of the country's largest franchise restaurant companies with 232 Pizza Hut locations. This is one example of WebRTC adoption today, but the potential is limitless when powered by IoT. Attendees will learn real-world benefits of WebRTC and explore future possibilities, as WebRTC and IoT intersect to improve customer service.
From telemedicine to smart cars, digital homes and industrial monitoring, the explosive growth of IoT has created exciting new business opportunities for real time calls and messaging. In his session at Internet of @ThingsExpo, Ivelin Ivanov, CEO and Co-Founder of Telestax, will share some of the new revenue sources that IoT created for Restcomm – the open source telephony platform from Telestax. Ivelin Ivanov is a technology entrepreneur who founded Mobicents, an Open Source VoIP Platform, to help create, deploy, and manage applications integrating voice, video and data. He is the co-founder of TeleStax, an Open Source Cloud Communications company that helps the shift from legacy IN/SS7 telco networks to IP-based cloud comms. An early investor in multiple start-ups, he still finds time to code for his companies and contribute to open source projects.
The Internet of Things (IoT) promises to create new business models as significant as those that were inspired by the Internet and the smartphone 20 and 10 years ago. What business, social and practical implications will this phenomenon bring? That's the subject of "Monetizing the Internet of Things: Perspectives from the Front Lines," an e-book released today and available free of charge from Aria Systems, the leading innovator in recurring revenue management.
The Internet of Things will put IT to its ultimate test by creating infinite new opportunities to digitize products and services, generate and analyze new data to improve customer satisfaction, and discover new ways to gain a competitive advantage across nearly every industry. In order to help corporate business units to capitalize on the rapidly evolving IoT opportunities, IT must stand up to a new set of challenges.
There’s Big Data, then there’s really Big Data from the Internet of Things. IoT is evolving to include many data possibilities like new types of event, log and network data. The volumes are enormous, generating tens of billions of logs per day, which raise data challenges. Early IoT deployments are relying heavily on both the cloud and managed service providers to navigate these challenges. In her session at 6th Big Data Expo®, Hannah Smalltree, Director at Treasure Data, to discuss how IoT, Big Data and deployments are processing massive data volumes from wearables, utilities and other machines.
All major researchers estimate there will be tens of billions devices – computers, smartphones, tablets, and sensors – connected to the Internet by 2020. This number will continue to grow at a rapid pace for the next several decades. With major technology companies and startups seriously embracing IoT strategies, now is the perfect time to attend @ThingsExpo in Silicon Valley. Learn what is going on, contribute to the discussions, and ensure that your enterprise is as "IoT-Ready" as it can be!
P2P RTC will impact the landscape of communications, shifting from traditional telephony style communications models to OTT (Over-The-Top) cloud assisted & PaaS (Platform as a Service) communication services. The P2P shift will impact many areas of our lives, from mobile communication, human interactive web services, RTC and telephony infrastructure, user federation, security and privacy implications, business costs, and scalability. In his session at Internet of @ThingsExpo, Erik Lagerway, Co-founder of Hookflash, will walk through the shifting landscape of traditional telephone and voice services to the modern P2P RTC era of OTT cloud assisted services.
While great strides have been made relative to the video aspects of remote collaboration, audio technology has basically stagnated. Typically all audio is mixed to a single monaural stream and emanates from a single point, such as a speakerphone or a speaker associated with a video monitor. This leads to confusion and lack of understanding among participants especially regarding who is actually speaking. Spatial teleconferencing introduces the concept of acoustic spatial separation between conference participants in three dimensional space. This has been shown to significantly improve comprehension and conference efficiency.
The Internet of Things is tied together with a thin strand that is known as time. Coincidentally, at the core of nearly all data analytics is a timestamp. When working with time series data there are a few core principles that everyone should consider, especially across datasets where time is the common boundary. In his session at Internet of @ThingsExpo, Jim Scott, Director of Enterprise Strategy & Architecture at MapR Technologies, will discuss single-value, geo-spatial, and log time series data. By focusing on enterprise applications and the data center, he will use OpenTSDB as an example to explain some of these concepts including when to use different storage models.
SYS-CON Events announced today that Gridstore™, the leader in software-defined storage (SDS) purpose-built for Windows Servers and Hyper-V, will exhibit at SYS-CON's 15th International Cloud Expo®, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Gridstore™ is the leader in software-defined storage purpose built for virtualization that is designed to accelerate applications in virtualized environments. Using its patented Server-Side Virtual Controller™ Technology (SVCT) to eliminate the I/O blender effect and accelerate applications Gridstore delivers vmOptimized™ Storage that self-optimizes to each application or VM across both virtual and physical environments. Leveraging a grid architecture, Gridstore delivers the first end-to-end storage QoS to ensure the most important App or VM performance is never compromised. The storage grid, that uses Gridstore’s performance optimized nodes or capacity optimized nodes, starts with as few a...
The Transparent Cloud-computing Consortium (abbreviation: T-Cloud Consortium) will conduct research activities into changes in the computing model as a result of collaboration between "device" and "cloud" and the creation of new value and markets through organic data processing High speed and high quality networks, and dramatic improvements in computer processing capabilities, have greatly changed the nature of applications and made the storing and processing of data on the network commonplace. These technological reforms have not only changed computers and smartphones, but are also changing the data processing model for all information devices. In particular, in the area known as M2M (Machine-To-Machine), there are great expectations that information with a new type of value can be produced using a variety of devices and sensors saving/sharing data via the network and through large-scale cloud-type data processing. This consortium believes that attaching a huge number of devic...
Innodisk is a service-driven provider of industrial embedded flash and DRAM storage products and technologies, with a focus on the enterprise, industrial, aerospace, and defense industries. Innodisk is dedicated to serving their customers and business partners. Quality is vitally important when it comes to industrial embedded flash and DRAM storage products. That’s why Innodisk manufactures all of their products in their own purpose-built memory production facility. In fact, they designed and built their production center to maximize manufacturing efficiency and guarantee the highest quality of our products.
Can call centers hang up the phones for good? Intuitive Solutions did. WebRTC enabled this contact center provider to eliminate antiquated telephony and desktop phone infrastructure with a pure web-based solution, allowing them to expand beyond brick-and-mortar confines to a home-based agent model. Download Slide Deck: ▸ Here
All major researchers estimate there will be tens of billions devices - computers, smartphones, tablets, and sensors - connected to the Internet by 2020. This number will continue to grow at a rapid pace for the next several decades. Over the summer Gartner released its much anticipated annual Hype Cycle report and the big news is that Internet of Things has now replaced Big Data as the most hyped technology. Indeed, we're hearing more and more about this fascinating new technological paradigm. Every other IT news item seems to be about IoT and its implications on the future of digital business.
BSQUARE is a global leader of embedded software solutions. We enable smart connected systems at the device level and beyond that millions use every day and provide actionable data solutions for the growing Internet of Things (IoT) market. We empower our world-class customers with our products, services and solutions to achieve innovation and success. For more information, visit www.bsquare.com.
With the iCloud scandal seemingly in its past, Apple announced new iPhones, updates to iPad and MacBook as well as news on OSX Yosemite. Although consumers will have to wait to get their hands on some of that new stuff, what they can get is the latest release of iOS 8 that Apple made available for most in-market iPhones and iPads. Originally announced at WWDC (Apple’s annual developers conference) in June, iOS 8 seems to spearhead Apple’s newfound focus upon greater integration of their products into everyday tasks, cross-platform mobility and self-monitoring. Before you update your device, here is a look at some of the new features and things you may want to consider from a mobile security perspective.