Welcome!

Apache Authors: Trevor Parsons, Sematext Blog , Lori MacVittie, Sandi Mappic, Carmen Gonzalez

News Feed Item

Commonwealth Silver and Gold Completes Positive Preliminary Economic Assessment for the Commonwealth Project, Cochise County, Arizona

TORONTO, ONTARIO -- (Marketwired) -- 02/13/14 -- Commonwealth Silver and Gold Mining Inc. ("Commonwealth Silver and Gold" or the "Company") is pleased to provide the results that will be reported in its Preliminary Economic Assessment ("PEA") for the 98% controlled Commonwealth gold and silver project in Cochise County, Arizona, approximately 120 km (75 miles) southeast of Tucson. The PEA was completed in accordance with National Instrument 43-101 ("NI 43-101") by Hard Rock Consulting, LLC ("HRC") of Lakewood, Colorado. All dollar amounts are in United States dollars unless otherwise stated.

All NPV amounts, IRR and payback period are based on the Company's 98% share of Project economics. All mining statistics, production, capital and closure amounts are to 100%. Highlights from the base case study at $1,350 per ounce gold, $22.50 per ounce silver and based solely on estimated Measured and Indicated mineral resources include:


--  Pre-tax Net Present Value ("NPV") at a 5% discount rate of $141.0
    million and a pre-tax Internal Rate of Return ("IRR") of 74.9%; 
--  After-tax NPV at a 5% discount rate of $101.3 million and IRR of 58.2%; 
--  After-tax payback of 1.6 years; 
--  Pre-production capital cost ("CAPEX") of $27.2 million including a 20%
    contingency; 
--  Remaining advance royalty payment $4.1 million and start-up working
    capital of $13.5 million until positive cash flow from leaching is
    achieved; 
--  Sustaining capital of $20.6 million (100%) over life of mine ("LOM")
    including a 20% contingency and reclamation, net of salvage values of
    $8.4 million; 
--  An 8.7 year mine life, mining and processing 31.2 million tonnes of ore
    at 10,000 tpd, averaging 0.39 grams per tonne ("g/t") gold and 32.0 g/t
    silver; 
--  An overall strip ratio of 0.97:1; 
--  Average annual payable metal production of 35,800 ounces of gold and 1.3
    million ounces of silver for total LOM production of approximately
    312,000 ounces of gold and 10.9 million ounces of silver;  
--  Average annual gold equivalent ("AuEq") production of 57,000 ounces AuEq
    at 60:1 gold to silver ratio, peaking at approximately 69,000 ounces
    AuEq in year 7; 
--  Gold Institute Cost Standard, LOM total cash operating costs are
    estimated to be approximately $831 per gold equivalent ounce; 
--  The HRC PEA has been constrained to the mineral resource estimate
    contained within a pit located entirely on the Company's patented mining
    claims and does not take into account the potential for additional
    mineralization on the adjoining unpatented mining claims or the
    potential for mineralization at the nearby Blue Jeep and San Ignacio
    exploration targets, all of which have the potential to extend the
    current projected life of the overall project or augment the economics
    of future years. Currently, there are no additional estimated mineral
    resources on any of these areas that are in compliance with NI 43-101. 

Michael Farrant, President and CEO stated, "We are extremely pleased with this Preliminary Economic Assessment. It demonstrates that the Commonwealth Project is one of the best undeveloped precious metals projects in the world based on after-tax IRR and after-tax NPV relative to the capital required to put the Project into production. The Project sits on private land in a mining friendly jurisdiction surrounded by first rate infrastructure. Most importantly, given the size of the Project relative to the market capitalization of the Company, this is a Project that can get built and those are exactly the kinds of projects that are retaining a superior valuation in the changing global mining landscape. The Commonwealth Project is currently projected to become the largest operating gold mine in the state of Arizona. As a Company, we have continued to deliver against our originally stated plans and I am very pleased with the work performed by everyone that contributed to the completion of this PEA."

The sensitivity table below shows the pre-tax and after-tax NPV, IRR and payback period at different gold prices, with the corresponding silver price calculated at a 60:1 gold to silver ratio.


----------------------------------------------------------------------------
                                                                      After-
                                           Pre-             Pre-tax      tax
Au Price    Ag Price   Pre-tax After-tax    tax    After-   Payback  Payback
Per Ounce  Per Ounce  NPV ($M)  NPV ($M)    IRR   tax IRR   (Years)  (Years)
----------------------------------------------------------------------------
$1,050      $  17.50  $   34.2  $   22.3   24.7%     18.6%      2.6      5.2
----------------------------------------------------------------------------
$1,125      $  18.75  $   60.9  $   42.7   38.2%     29.6%      2.2      2.5
----------------------------------------------------------------------------
$1,200      $  20.00  $   87.7  $   62.4   50.9%     39.6%      1.8      2.1
----------------------------------------------------------------------------
$1,275      $  21.25  $  114.3  $   81.8   63.1%     49.1%      1.5      1.8
----------------------------------------------------------------------------
$1,350      $  22.50  $  141.0  $  101.3   74.9%     58.2%      1.3      1.6
----------------------------------------------------------------------------
$1,425      $  23.75  $  167.7  $  120.4   86.5%     67.0%      1.0      1.4
----------------------------------------------------------------------------
$1,500      $  25.00  $  194.4  $  138.7   97.9%     75.1%      1.0      1.3
----------------------------------------------------------------------------
$1,575      $  26.25  $  221.1  $  156.4  109.1%     82.4%      0.8      1.1
----------------------------------------------------------------------------
$1,650      $  27.50  $  247.7  $  174.1  120.3%     89.7%      0.7      1.0
----------------------------------------------------------------------------
                                                                         
                                                                         
Table 1: Mine Plan Highlights                                            
                                                                         
-------------------------------------------------------------------------
Summary of Results                                  Unit            Value
-------------------------------------------------------------------------
Mine Life                                          Years              8.7
-------------------------------------------------------------------------
Total ore to leach pads                         M tonnes             31.2
-------------------------------------------------------------------------
Total waste                                     M tonnes             30.3
-------------------------------------------------------------------------
Strip ratio                                          w:o           0.97:1
-------------------------------------------------------------------------
Total re-handled                                M tonnes              5.3
-------------------------------------------------------------------------
Total moved                                     M tonnes             66.8
-------------------------------------------------------------------------
Ore mining rate                                      tpd           10,000
-------------------------------------------------------------------------
Average grade to pad - Au                            g/t             0.39
-------------------------------------------------------------------------
Average grade to pad - Ag                            g/t             32.0
-------------------------------------------------------------------------
Cumulative recovery - Au                              %             79.5%
-------------------------------------------------------------------------
Cumulative recovery - Ag                              %             34.2%
-------------------------------------------------------------------------
LOM production - Au                               ounces          311,534
-------------------------------------------------------------------------
LOM production - Ag                               ounces       10,926,367
-------------------------------------------------------------------------
LOM production - AuEq (60:1)                      ounces          493,640
-------------------------------------------------------------------------
Average annual production - Au                    ounces           35,809
-------------------------------------------------------------------------
Average annual production - Ag                    ounces        1,255,904
-------------------------------------------------------------------------
Average annual production - AuEq (60:1)           ounces           56,740
-------------------------------------------------------------------------
-------------------------------------------------------------------------
                                                                            
                                                                            
Table 2: Economic Highlights                                                
                                                                            
----------------------------------------------------------------------------
Summary of Results                                Value ($ M)      $/oz AuEq
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
 LOM revenue - ($1,350/oz. Au, $22.50/oz. Ag)          $666.4         $1,350
----------------------------------------------------------------------------
 LOM operating costs:                                                       
----------------------------------------------------------------------------
  Mining (including 2.5% contingency)                   182.2            369
----------------------------------------------------------------------------
  Processing (including 2.5% contingency)               190.9            387
----------------------------------------------------------------------------
  Site G&A (including 2.5% contingency)                  19.9             40
----------------------------------------------------------------------------
  Property and other taxes                                5.3             10
----------------------------------------------------------------------------
  Royalties                                               8.2             17
----------------------------------------------------------------------------
  Transportation and refining                             3.8              8
----------------------------------------------------------------------------
Total LOM cash operating costs                          410.3            831
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Capital and closure costs:                                                  
----------------------------------------------------------------------------
  Pre-production capital                                 23.0             46
----------------------------------------------------------------------------
  Pre-production contingency (20%)                        4.2              9
----------------------------------------------------------------------------
Total pre-production capital                             27.2             55
----------------------------------------------------------------------------
  Sustaining capital                                     17.2             35
----------------------------------------------------------------------------
  Sustaining capital contingency (20%)                    3.4              7
----------------------------------------------------------------------------
Total sustaining capital                                 20.6             42
----------------------------------------------------------------------------
Closure costs net of salvage values                       8.4             17
----------------------------------------------------------------------------
Total capital and closure costs (including                                  
 contingency)                                            56.2            114
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Other cash outflows:                                                        
----------------------------------------------------------------------------
  Income taxes                                           53.5            108
----------------------------------------------------------------------------
  Other                                                   4.1              8
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Total after-tax cash flow                              $142.3           $289
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Unit costs                                               Unit          Value
----------------------------------------------------------------------------
  Cost per tonne mined - 61,426,774 tonnes            $/tonne          $2.97
----------------------------------------------------------------------------
  Cost per tonne processed - 31,153,575                                     
   tonnes                                             $/tonne          $6.13
----------------------------------------------------------------------------
  Cost per tonne site G&A - 31,153,575 tonnes         $/tonne          $0.64
----------------------------------------------------------------------------
----------------------------------------------------------------------------

Mineral Resource Statement for the Commonwealth Gold and Silver Project:

The Mineral Resource estimate, before designing an engineered pit, is based on a 3D geologic model constructed using geologic and assay data from approximately 23,085 meters of drilling in 208 drill holes (155 historic and 43 drilled by the Company) and 2,984 meters of channel sampling in 209 channel sample lines. The assay data was examined for the presence of high grade outlier data which could potentially adversely impact the grade estimation. Based on this analysis, all gold and silver assays were capped at 10.0 g/t and 1,000.0 g/t, respectively. The capped assay data were then composited into 4.0m down-hole lengths for use in grade estimation. Block grades were estimated using inverse distance weighting ("IDW") interpolation methods, specifically ID2.5. The Mineral Resource estimate stated above a 0.2 g/t gold equivalent ("AuEq") cut-off grade is stated below in Table 3.


                                                                            
Table 3: Mineral Resource Statement for the Commonwealth Gold-Silver        
Deposit, Cochise County, Arizona, Hard Rock Consulting, LLC, November 30,   
2013(i)                                                                     
----------------------------------------------------------------------------
                                                    Contained Metal (Ounces)
                                          ----------------------------------
                       Au       Ag    AuEq                                  
Cut-off     Tonnes   Grade   Grade   Grade                                  
(g/t)       ('000)   (g/t)   (g/t)   (g/t)        Au           Ag       AuEq
----------------------------------------------------------------------------
            Inverse Distance 2.5 Model In Pit Measured Resources            
----------------------------------------------------------------------------
0.4          4,069    0.57    48.6    1.38    74,800    6,357,700    180,800
----------------------------------------------------------------------------
0.3          4,504    0.53    45.0    1.28    77,200    6,516,900    185,700
----------------------------------------------------------------------------
0.2          5,007    0.49    41.3    1.18    79,000    6,648,500    189,800
----------------------------------------------------------------------------
            Inverse Distance 2.5 Model In Pit Indicated Resources           
----------------------------------------------------------------------------
0.4         21,934    0.45    36.8    1.06   314,500   25,950,900    746,100
----------------------------------------------------------------------------
0.3         26,643    0.40    32.2    0.93   339,200   27,582,000    799,200
----------------------------------------------------------------------------
0.2         30,623    0.36    29,1    0.85   354,400   28,650,600    832,000
----------------------------------------------------------------------------
                   In Pit Measured and Indicated Resources                  
----------------------------------------------------------------------------
0.4         26,003    0.47    38.6    1.11   389,300   32,308,600    926,900
----------------------------------------------------------------------------
0.3         31,147    0.42    34.1    0.98   416,400   34,098,900    984,900
----------------------------------------------------------------------------
0.2         35,630    0.38    30.8    0.89   433,400   35,299,100  1,021,800
----------------------------------------------------------------------------
                Inverse Distance 2.5 Model Inferred Resources               
----------------------------------------------------------------------------
0.4          7,380    0.29    17.2    0.58    67,900    4,075,100    136,700
----------------------------------------------------------------------------
0.3         12,974    0.25    13.8    0.48   102,800    5,762,000    199,600
----------------------------------------------------------------------------
0.2         18,733    0.21    11.6    0.41   127,600    6,998,200    245,400
----------------------------------------------------------------------------


(i)Notes:                                                                   
(1) Mineral Resources are not Mineral Reserves and do not have demonstrated 
economic viability. There is no certainty that all or any part of the       
Mineral Resources estimated will be converted into Mineral Reserves.        
(2) Measured and Indicated Mineral Resources captured within the pit shell  
meet the test of reasonable prospect for economic extraction and can be     
declared a Mineral Resource.                                                
(3) Inferred Mineral Resources are that part of the Mineral Resource for    
which the quantity and grade or quality are estimated on the basis of       
geological evidence and limited sampling and reasonably assumed, but not    
verified, geological and grade continuity.                                  
(4) All resources are stated above a 0.2 g/t gold equivalent ("AuEq") cut-  
off.                                                                        
(5) Pit optimization is based on assumed gold and silver prices of          
US$1,350/oz. and US$22.50/oz., respectively and mining, processing and G&A  
costs of US$7.25 per tonne. Metallurgical recoveries for gold and silver    
were assigned by lithologic unit.                                           
(6) Mineral resource tonnage and contained metal have been rounded to       
reflect the accuracy of the estimate, and numbers may not add due to        
rounding.                                                                   
(7) Gold Equivalent stated using a ratio of 60:1 and ounces calculated using
the following conversion rate: 1 troy ounce = 31.1035 grams. Metallurgical  
recoveries are not accounted for in the gold equivalent calculation.        

Mineral Resource Estimates Used for Economic Assessment in the PEA:

The estimated Mineral Resource contained within the PEA includes 28.3 million tonnes at a 0.3 g/t AuEq cut-off and an additional 2.8 million tonnes of lower grade ore at a 0.24 g/t AuEq cut-off and is presented in Table 4. This represents the estimated Mineral Resource contained within the preliminary engineered pit design which includes haul roads. The PEA is preliminary in nature and it is important to note that the Mineral Resources described herein are not mineral reserves and, as such, do not have demonstrated economic viability. There is no certainty that the preliminary economic assessment will be realized.


                                                                            
Table 4: Measured and Indicated Resources within Pit Design                 
----------------------------------------------------------------------------
                                                    Contained Metal (Ounces)
                                               -----------------------------
                                Au     Ag  AuEq                             
Pit      Resource     Tonnes Grade  Grade Grade                             
 Phase    Category    ('000) (g/t)  (g/t) (g/t)      Au          Ag     AuEq
----------------------------------------------------------------------------
Phase 1  Measured      3,253  0.46  43.07  1.18  48,034   4,504,874  123,115
----------------------------------------------------------------------------
Phase 1  Indicated    12,227  0.36  34.57  0.94 142,539  13,590,165  369,042
----------------------------------------------------------------------------
         Measured +                                                         
Phase 1   Indicated   15,480  0.38  36.36  0.99 190,573  18,095,039  492,157
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Phase 2  Measured      1,633  0.56  38.17  1.19  29.212   2,003,915   62,610
----------------------------------------------------------------------------
Phase 2  Indicated    14.040  0.38  26.37  0.82 172,644  11,902,972  371,027
----------------------------------------------------------------------------
         Measured +                                                         
Phase 2   Indicated   15,673  0.40  27.60  0.86 201,856  13,906,886  433,637
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total                                                                       
 All                                                                        
 Phases  Measured      4,886  0.49  41.43  1.18  77,245   6,508,788  185,725
----------------------------------------------------------------------------
Total                                                                       
 All                                                                        
 Phases  Indicated    26,267  0.37  30.19  0.88 315,184  25,493,137  740,069
----------------------------------------------------------------------------
Total                                                                       
 All     Measured +                                                         
 Phases   Indicated   31,154  0.39  31.95  0.92 392,429  32,001,925  925,794
----------------------------------------------------------------------------
----------------------------------------------------------------------------
1) Mineral Resources are not Mineral Reserves and do not have demonstrated  
economic viability. There is no certainty that all or any part of the       
Mineral Resources estimated will be converted into Mineral Reserves.        
2) Prepared by Jeff Choquette, P.E., Mining Engineer, an independent        
Qualified Person within the meaning of NI 43-101, using a reporting cut-off 
grade of 0.24 g/t AuEq.                                                     
3) Gold Equivalent stated using a ratio of 60:1 and ounces calculated using 
the following conversion rate: 1 troy ounce = 31.1035 grams.  Metallurgical 
recoveries are not accounted for in the gold equivalent calculation.        

(i)Total Measured and Indicated ("M&I") resources are inclusive of the M&I resources limited to the optimized ultimate pit boundary and as such Table 4 summarizes resources contained within the pit design only.

Mining and Crushing

The mine plan developed for the PEA mines the Commonwealth deposit in two phases. The phase one pit containing 15.48 million ore tonnes is mined during years 1 to 4. During years 1 to 3, the average strip ratio is 0.66:1. During year 4, mining begins to transition into the phase two pit containing 15.67 million ore tonnes. The average strip ratio over years 4 to 6 is 1.66:1 while during years 7 to 9 the average strip ratio falls to 0.42:1.

Standard open pit mining methods are utilized involving typical drilling, blasting and material movement. The 31.2 million ore tonnes to be placed on the leach pads are comprised of five different rock types. Three of these rock types comprising 19.43 million ore tonnes (62%) are required to be crushed to 1/2 inch. Two of these rock types comprising 11.72 million ore tonnes (38%) are required to be crushed to 1/8 inch and agglomerated.


                                                                            
Table 5: Crush Size, Recovery and Ore Tonnage by Rock Type                  
-------------------------------------------------------------
                                  Recoveries (%)             
-------------------------------------------------------------
Rock Type          Crush Size       Au        Ag   Tonnes (M)
-------------------------------------------------------------
Rhyolite                 1/8"     78.0      30.0         7.34
-------------------------------------------------------------
Vein                     1/8"     79.0      49.0         4.38
-------------------------------------------------------------
Lower Andesite           1/2"     81.0      33.0         4.63
-------------------------------------------------------------
Upper Andesite           1/2"     78.0      35.0         6.11
-------------------------------------------------------------
Bisbee                   1/2"     80.0      23.0         8.69
-------------------------------------------------------------
Total                             79.5      34.2        31.15
-------------------------------------------------------------

The Company received a quote from a contractor to perform all of the drilling, blasting, material movement and crushing to mine plan specifications. This quote has been included in the PEA.

Processing

The Commonwealth Project will use a (flow rate) Merrill-Crowe gold and silver recovery plant using zinc precipitation to recover gold and silver from cyanide solution. The process plant will operate 24 hours per day and 365 days per year at a rate of 3,000 gallons per minute. The process plant will produce dore with approximately 97% of the precious metal content being silver and 3% being gold.

Infrastructure

The Commonwealth Project is accessible by paved highway. Currently a 14.4 KvA powerline services the property with 60 amp service. The PEA envisions upgrading the trunk powerline from the Apache Generating Station located 19km (11 miles) from the Project site at a cost of approximately $358,000. Water is planned to be sourced from regional groundwater sources.

Capital Costs

The initial capital requirement for the Project to 100% is estimated to be $27.2 million, sustaining capital of $20.6 million and net closure costs of $8.4 million as detailed in the table below. A contingency of $7.6 million is included in the $56.2 million total.


                                                                            
Table 6: Commonwealth Project Capital and Closure Costs                     
--------------------------------------------------------------
Capital and Closure Costs                         $ (millions)
--------------------------------------------------------------
Pre-production Capital Costs                                  
--------------------------------------------------------------
Conveying equipment                                        4.8
--------------------------------------------------------------
Merrill-Crowe plant and equipment                          2.5
--------------------------------------------------------------
Truck shop, assay lab and buildings                        4.5
--------------------------------------------------------------
Haul roads and access road                                 1.2
--------------------------------------------------------------
Leach pad and ponds                                        4.9
--------------------------------------------------------------
Off-site infrastructure                                    0.7
--------------------------------------------------------------
Owner's cost and indirects                                 3.1
--------------------------------------------------------------
Surface rights                                             1.3
--------------------------------------------------------------
Total pre-production initial capital costs                23.0
--------------------------------------------------------------
Contingency                                                4.2
--------------------------------------------------------------
Total pre-production capital costs                        27.2
--------------------------------------------------------------
Sustaining Capital Costs                                      
--------------------------------------------------------------
Leach pads                                                 8.9
--------------------------------------------------------------
Merrill-Crowe plant and equipment                          8.3
--------------------------------------------------------------
Contingency                                                3.4
--------------------------------------------------------------
Total sustaining capital                                  20.6
--------------------------------------------------------------
Reclamation and closure costs                             12.3
--------------------------------------------------------------
Salvage values - mine and other                          (2.6)
--------------------------------------------------------------
Salvage values - land                                    (1.3)
--------------------------------------------------------------
Closure costs net of salvage values                        8.4
--------------------------------------------------------------
Total capital and closure costs                           56.2
--------------------------------------------------------------

Financial Analysis and Sensitivities

Using a gold price of $1,350 per ounce and a silver price of $22.50 per ounce, the PEA yields a pre-tax NPV at 5% of $141.0 million and IRR of 74.9% with a payback period of 1.3 years. After-tax NPV at 5% amounts to $101.3 million, and IRR of 58.2% and a payback period of 1.6 years.


Table 7: Project NPV Sensitivity to Discount Rates                          
------------------------------------------------
Discount Rate      Pre-tax NPV     After-tax NPV
------------------------------------------------
0%                      $195.8            $142.3
------------------------------------------------
5%                      $141.0            $101.3
------------------------------------------------
8%                      $115.6             $82.0
------------------------------------------------
10%                     $101.3             $71.2
------------------------------------------------

Qualified Persons and Contributors

The Technical Report and Preliminary Economic Assessment for the Commonwealth Silver and Gold Project was prepared by Hard Rock Consulting, LLC of Lakewood, Colorado, with the following Qualified Persons, as defined by NI 43-101, each of whom is independent of the Company, contributing to their respective sections:

Qualified Persons

Zachary Black - QP-SME-RM, Geology, Resource Modeling

J. J. Brown - P.G., QP-SME-RM, Geology, Overall Report Content

Jeff Choquette - P.E., QP-MMSA, Mine Planning, Economic Modelling, Mine Management

Deepak Malhotra, Resource Development Inc - Ph.D., QP-MMSA, Metallurgy

Additional Contributors:

Don Beesley - B.Sc., Project Management, Scheduling, Estimating

Mark Shonnard - B.A. (Hons), CPA, Economic Modeling, Financial Analysis

Kenn Zerby - B.Sc., Mechanical Engineering, Graphics and Drafting

Each of the consultants has reviewed and approved this news release. In addition, the foregoing technical information has also been reviewed by Mr. Hall Stewart, Vice President, Exploration for Commonwealth Silver and Gold and a Qualified Person for the purpose of NI 43-101.

Technical Report

A copy of the full NI 43-101 Technical Report will be available on the Company's website at www.commonwealthsilver.ca within 45 days.

About Commonwealth Silver and Gold Mining Inc.

Commonwealth Silver and Gold is a private Canadian mineral exploration and development company focused on acquiring gold and silver properties in politically stable, mining friendly jurisdictions and advancing its flagship Commonwealth Project in Arizona towards production. The Company comprises an experienced management group with a strong background in acquisition, exploration, development and financing of precious metals mining projects.

For further information on Commonwealth Silver and Gold please visit www.commonwealthsilver.ca.

CAUTIONARY NOTE TO U.S. INVESTORS CONCERNING ESTIMATES OF MEASURED, INDICATED AND INFERRED MINERAL RESOURCES:

Information concerning the properties of Commonwealth Silver and Gold has been prepared in accordance with Canadian standards under applicable Canadian securities laws and may not be comparable to similar information for United States companies. This news release uses the terms "Mineral Resource", "Measured Mineral Resource", "Indicated Mineral Resource" and "Inferred Mineral Resource" which are Canadian mining terms as defined in and required to be disclosed by NI 43-101 under guidelines set out in the CIM standard "CIM Definition Standards - For Mineral Resources and Reserves". While the terms "Mineral Resource", "Measured Mineral Resource", "Indicated Mineral Resource" and "Inferred Mineral Resource" are recognized and required by Canadian regulations, they are not defined terms under standards of the United States Securities and Exchange Commission (the "SEC"). The estimation of measured and indicated Mineral Resources involves greater uncertainty as to their existence and economic feasibility than the estimation of proven and probable reserves. U.S. investors are cautioned not to assume that measured and indicated Mineral Resources will be converted into reserves. The estimation of inferred Mineral Resources involves far greater uncertainty as to their existence and economic viability than the other categories of estimated Mineral Resources. It cannot be assumed that all or any part of an "Inferred Mineral Resource" will ever be upgraded to a higher category. Under Canadian rules, estimates of Inferred Mineral Resources may not form the basis of feasibility or other economic studies. Readers are also cautioned not to assume that all or any part of Measured or Indicated Resources will ever be converted to Mineral Reserves. Additionally, readers are cautioned not to assume that all or any part of an "Inferred Mineral Resource" exists, or is economically mineable.

Disclosure of "contained ounces" in an estimated Mineral Resource is permitted disclosure under Canadian regulations, however the SEC normally only permits issuers to report mineralization that does not constitute "reserves" by SEC standards as in place tonnage and grade without reference to unit measures. Accordingly, the information contained in this news release may not be comparable to similar information made public by U.S. companies that are not subject to NI 43-101.

CAUTIONARY NOTE REGARDING FORWARD LOOKING INFORMATION

This news release contains certain "forward-looking information" under Canadian securities laws. All statements that address future plans, activities, events or developments that the Company believes, expects or anticipates will or may occur are forward-looking information. This can include, but is not limited to comments regarding the timing and content of upcoming work programs, geological interpretations, receipt of property titles, potential mineral recovery processes etc. Forward-looking information addresses future events and conditions and therefore involves inherent risks and uncertainties. There can be no assurance that outcomes anticipated in the forward-looking information will occur and actual results may differ materially from those currently anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking information. The Company undertakes no obligation to update publicly or otherwise any forward-looking information, except as may be required by law.

No stock exchange, regulation securities provider, securities commission or other regulatory authority has approved or disapproved the information contained in this news release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
The BPM world is going through some evolution or changes where traditional business process management solutions really have nowhere to go in terms of development of the road map. In this demo at 15th Cloud Expo, Kyle Hansen, Director of Professional Services at AgilePoint, shows AgilePoint’s unique approach to dealing with this market circumstance by developing a rapid application composition or development framework.

ARMONK, N.Y., Nov. 20, 2014 /PRNewswire/ --  IBM (NYSE: IBM) today announced that it is bringing a greater level of control, security and flexibility to cloud-based application development and delivery with a single-tenant version of Bluemix, IBM's platform-as-a-service. The new platform enables developers to build ap...

"BSQUARE is in the business of selling software solutions for smart connected devices. It's obvious that IoT has moved from being a technology to being a fundamental part of business, and in the last 18 months people have said let's figure out how to do it and let's put some focus on it, " explained Dave Wagstaff, VP & Chief Architect, at BSQUARE Corporation, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4-6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
The major cloud platforms defy a simple, side-by-side analysis. Each of the major IaaS public-cloud platforms offers their own unique strengths and functionality. Options for on-site private cloud are diverse as well, and must be designed and deployed while taking existing legacy architecture and infrastructure into account. Then the reality is that most enterprises are embarking on a hybrid cloud strategy and programs. In this Power Panel at 15th Cloud Expo (http://www.CloudComputingExpo.com), moderated by Ashar Baig, Research Director, Cloud, at Gigaom Research, Nate Gordon, Director of T...
The Internet of Things is not new. Historically, smart businesses have used its basic concept of leveraging data to drive better decision making and have capitalized on those insights to realize additional revenue opportunities. So, what has changed to make the Internet of Things one of the hottest topics in tech? In his session at @ThingsExpo, Chris Gray, Director, Embedded and Internet of Things, discussed the underlying factors that are driving the economics of intelligent systems. Discover how hardware commoditization, the ubiquitous nature of connectivity, and the emergence of Big Data a...
SYS-CON Events announced today that Windstream, a leading provider of advanced network and cloud communications, has been named “Silver Sponsor” of SYS-CON's 16th International Cloud Expo®, which will take place on June 9–11, 2015, at the Javits Center in New York, NY. Windstream (Nasdaq: WIN), a FORTUNE 500 and S&P 500 company, is a leading provider of advanced network communications, including cloud computing and managed services, to businesses nationwide. The company also offers broadband, phone and digital TV services to consumers primarily in rural areas.
“In the past year we've seen a lot of stabilization of WebRTC. You can now use it in production with a far greater degree of certainty. A lot of the real developments in the past year have been in things like the data channel, which will enable a whole new type of application," explained Peter Dunkley, Technical Director at Acision, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today that IDenticard will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. IDenticard™ is the security division of Brady Corp (NYSE: BRC), a $1.5 billion manufacturer of identification products. We have small-company values with the strength and stability of a major corporation. IDenticard offers local sales, support and service to our customers across the United States and Canada. Our partner network encompasses some 300 of the world's leading systems integrators and security s...
DevOps Summit 2015 New York, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that produce software that is obsolete at launch. DevOps may be disruptive, but it is essential.
"People are a lot more knowledgeable about APIs now. There are two types of people who work with APIs - IT people who want to use APIs for something internal and the product managers who want to do something outside APIs for people to connect to them," explained Roberto Medrano, Executive Vice President at SOA Software, in this SYS-CON.tv interview at Cloud Expo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
Nigeria has the largest economy in Africa, at more than US$500 billion, and ranks 23rd in the world. A recent re-evaluation of Nigeria's true economic size doubled the previous estimate, and brought it well ahead of South Africa, which is a member (unlike Nigeria) of the G20 club for political as well as economic reasons. Nigeria's economy can be said to be quite diverse from one point of view, but heavily dependent on oil and gas at the same time. Oil and natural gas account for about 15% of Nigera's overall economy, but traditionally represent more than 90% of the country's exports and as...
The Internet of Things is a misnomer. That implies that everything is on the Internet, and that simply should not be - especially for things that are blurring the line between medical devices that stimulate like a pacemaker and quantified self-sensors like a pedometer or pulse tracker. The mesh of things that we manage must be segmented into zones of trust for sensing data, transmitting data, receiving command and control administrative changes, and peer-to-peer mesh messaging. In his session at @ThingsExpo, Ryan Bagnulo, Solution Architect / Software Engineer at SOA Software, focused on desi...
"At our booth we are showing how to provide trust in the Internet of Things. Trust is where everything starts to become secure and trustworthy. Now with the scaling of the Internet of Things it becomes an interesting question – I've heard numbers from 200 billion devices next year up to a trillion in the next 10 to 15 years," explained Johannes Lintzen, Vice President of Sales at Utimaco, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
"For over 25 years we have been working with a lot of enterprise customers and we have seen how companies create applications. And now that we have moved to cloud computing, mobile, social and the Internet of Things, we see that the market needs a new way of creating applications," stated Jesse Shiah, CEO, President and Co-Founder of AgilePoint Inc., in this SYS-CON.tv interview at 15th Cloud Expo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today that Gridstore™, the leader in hyper-converged infrastructure purpose-built to optimize Microsoft workloads, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Gridstore™ is the leader in hyper-converged infrastructure purpose-built for Microsoft workloads and designed to accelerate applications in virtualized environments. Gridstore’s hyper-converged infrastructure is the industry’s first all flash version of HyperConverged Appliances that include both compute and storag...
Today’s enterprise is being driven by disruptive competitive and human capital requirements to provide enterprise application access through not only desktops, but also mobile devices. To retrofit existing programs across all these devices using traditional programming methods is very costly and time consuming – often prohibitively so. In his session at @ThingsExpo, Jesse Shiah, CEO, President, and Co-Founder of AgilePoint Inc., discussed how you can create applications that run on all mobile devices as well as laptops and desktops using a visual drag-and-drop application – and eForms-buildi...
We certainly live in interesting technological times. And no more interesting than the current competing IoT standards for connectivity. Various standards bodies, approaches, and ecosystems are vying for mindshare and positioning for a competitive edge. It is clear that when the dust settles, we will have new protocols, evolved protocols, that will change the way we interact with devices and infrastructure. We will also have evolved web protocols, like HTTP/2, that will be changing the very core of our infrastructures. At the same time, we have old approaches made new again like micro-services...
Code Halos - aka "digital fingerprints" - are the key organizing principle to understand a) how dumb things become smart and b) how to monetize this dynamic. In his session at @ThingsExpo, Robert Brown, AVP, Center for the Future of Work at Cognizant Technology Solutions, outlined research, analysis and recommendations from his recently published book on this phenomena on the way leading edge organizations like GE and Disney are unlocking the Internet of Things opportunity and what steps your organization should be taking to position itself for the next platform of digital competition.
The 3rd International Internet of @ThingsExpo, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that its Call for Papers is now open. The Internet of Things (IoT) is the biggest idea since the creation of the Worldwide Web more than 20 years ago.
As the Internet of Things unfolds, mobile and wearable devices are blurring the line between physical and digital, integrating ever more closely with our interests, our routines, our daily lives. Contextual computing and smart, sensor-equipped spaces bring the potential to walk through a world that recognizes us and responds accordingly. We become continuous transmitters and receivers of data. In his session at @ThingsExpo, Andrew Bolwell, Director of Innovation for HP's Printing and Personal Systems Group, discussed how key attributes of mobile technology – touch input, sensors, social, and ...